Digital Realty Singapore uses electrolysis to clean its cooling water

https://www.datacenterdynamics.com/en/news/digital-realty-singapore-uses-electrolysis-to-clean-its-cooling-water/

SIN10 cooling water can be used three times as long

50 points · 1 comments · view on lemmy.world

1 Comments

VulcanSphere@kbin.social · 5 pts · 3y

Ng told us that each DCI unit costs around SG$33,000 (US$25,000) and can treat - very roughly - enough water for about 1MW to 1.3MW of cooling infrastructure. To cover the whole output of SIN10 would therefore need 20 to 25 DCI units, which suggests a cost of maybe US$500,000, although no figures have been quoted to us for the deal.

The installation was partially funded by a Singapore government program to save water, and Digital claims it saves 1.24 million liters of water per month.