(everyone knows roading budgets usually blow out - the total final cost of Transmission Gully appears to be $2.5bn – double the projected cost of $1.25bn).
$22 billion on just one 95km road ($232 million per km)
https://www.greaterauckland.org.nz/2026/03/03/22000000000-on-just-one-road/
10 Comments
Dave@lemmy.nz · 7 pts · 152d
How many years of free public transport would $22B buy?
I recall the 50% price cut during COVID (for the whole country) cost the government a few hundred million for a year. This was during COVID so it didn't get higher uptake, but let's assume there was a higher uptake and make it $500M for 50% off per year, or 1B for free public transport per year.
We could have free public transport for everyone for 22 years for the price of this one road.
rimu@piefed.social · 9 pts · 152d
In the article they came up with a few other things 22B would buy:
deadbeef79000@lemmy.nz · 2 pts · 149d
It buys a hell of a lot of post-parliamentary corporate directorships.
Dave@lemmy.nz · 2 pts · 148d
We really need a better way of managing this risk. I don't have any suggestions but the blatant bribery is a pretty big problem to democracy.
philanthropicoctopus@thelemmy.club · 5 pts · 152d
How much is that per centimeter?
freshcow@lemmy.world · 4 pts · 152d
$2320 per cm; or $232 per mm
philanthropicoctopus@thelemmy.club · 2 pts · 149d
Thanks
That's absolutely insane. Imagine if that was the number in the proposed plan. Would have been squashed instantly
BaconWrappedEnigma@lemmy.nz · 3 pts · 152d
Is anybody held accountable or are there any incentive structures to prevent it from happening in the future?
rimu@piefed.social · 2 pts · 152d
8 months till the election. They haven't started work on this yet so it'll probably come to nothing if they lose.
GGNZ@lemmy.nz · 2 pts · 144d
I saw this recently
"Even so, the numbers are staggering. The section between Whangarei and Te Hana is expected to cost $15.3-18.3 billion, and this doesn’t include the cost of the Warkworth to Te Hana section which is expected to start construction next year and was most recently estimated to cost $2.9-3.8 billion.
Combined, that’s $18.2-22.1 billion – which is incredible for a road that for most of its length carries only 10-15,000 vehicles a day.
To put the cost a different way: if usage of the road more than doubled to 30k vehicles per day (which is more than most parts of the Waikato Expressway) over a 30 year span, that would still work out at nearly $70 per trip include the cost of operating and maintaining the road."
https://www.greaterauckland.org.nz/2025/10/21/rons-reality-needs-to-bite/